Kitchen and Dining Hall Renovations

Working...

Ajax Loading Image

 


Skip image

 Story image 1_0
5a62569b098a4 New entrance!
Pouring of the footing
Plumbing and Electrical done by Scott Erb & Orlin Martens
Pouring of concrete
Framing of the walls
Interior framing
Addition of windows and Tyvek
Foam insulation completion
Beginning the work of stucco
Completed south wall
Completed additional 22 feet
Gutting of the old kitchen area
Removal of the built-in walk-in fridge
Items (to keep) from the old kitchen in Dining Hall "temporary storage"
Framing and roofing of new Dining Hall entrance
Kitchen interior framing
Kitchen interior framing
Kitchen interior walls
New entrance!

Kitchen and Dining Hall Renovations

Kitchen and Dining Hall Renovations

Join us as we enhance the Camp Mennoscah Kitchen, Dining Hall, and Entrance!  The Camp Mennoscah dining hall and kitchen have always been a place of gathering.  Through these updates, we are seeking to provide space for new meaningful experiences in these areas while also honoring the traditions they have held for many years.

entrance renderingaerial rendering

After a busy start to the year, much cleaning, and arranging new equipment, we dedicated the new, completed main camp kitchen this April, and it has already been in use! Updates to the dining hall will come next, but they will wait until after the camping season winds down in the fall. The new welcome area is mostly complete but will remain unfinished until we start in on the dining hall renovations, with estimated completion by April 2019. The next time you are at camp, you will be greeted by the new covered entrance to the dining hall! We are excited about how this new feature will provide a clear point of entry into the dining hall for new guests. We are still working toward our fundraising goal of $553,000 for the entire project. Thanks for considering support for the kitchen and dining hall!

Help us “Fill the Pitcher” by clicking the “Donate” button above, and follow our progress!

pitcher graphic

Project Budget
Project Cost Completion Date
Kitchen, new construction $66,300 Completed
Kitchen, interior and equipment $212,100 Completed
Covered Entrance and welcome area $77,300 April 2019
Dining Hall $147,300 April 2019
Contingency $50,000  
TOTAL $553,000 April 2019

Floor Plan

Kitchen and Entrance

  • Construction of new addition to existing kitchen space - completed
  • Interior remodel of entire kitchen space - completed
  • New equipment (stoves, ovens, walk-in refrigerator and freezer, etc.) - completed
  • Construction of new covered entrance - completed
  • Heating, ventilation, and air conditioning - in progress

Dining Hall

  • Construction of new welcome area - in progress
  • Updates to floor surface
  • New windows
  • Insulation and noise dampening material in ceiling
  • Heating, ventilation, and air conditioning

How you can be involved!

  • Donate to help us reach our funding goal by clicking the “Donate” button at the top of this page.
  • Volunteer your time in specific areas during the project. Contact Camp Mennoscah for details.
  • Share about the project with family and friends!
  • Pray that God will be present throughout this project and will bless Camp Mennoscah’s ministry through it.

Back To Top